Final fettling, prep and etch priming the last four half-drop window frames was the work for today.
All posts by Nigel
28/1/2020
The last few days have been all about making the timbers for the wheelarch framing. I have now managed to assemble the forward half of the wheelarch frame, including a new steel flitch plate, and have finally aligned the lower perimeter rails with the rear of the bus so the sides will be straight as Weymann intended.
The rear half of the wheelarch cannot be assembled until I have replaced the lower half of the first side rod behind the wheel opening.
23/1/2020
Today has been spent continuing to manufacture the timbers to rebuild the nearside wheelarch. The parts are mostly complete, I need to make the packing that gives shape to the outer face of the pillars and then give the parts not treated a good soak in preservative.